A contract is to be completed in 56 days if 104 persons work, each working at 8 hours a day. After 30 days, 2/5 of the work is completed. How many additional persons should be deployed so that the work will be completed in the scheduled time,each persons now working 9 hours a day?

General Knowledge General in General Knowledge . 2 years ago

  23   0   1   0   0 tuteeHUB earn credit +10 pts

5 Star Rating 1 Rating

Posted on 12 Dec 2021, this text provides information on General Knowledge related to General in General Knowledge. Please note that while accuracy is prioritized, the data presented might not be entirely correct or up-to-date. This information is offered for general knowledge and informational purposes only, and should not be considered as a substitute for professional advice.

Take Quiz To Earn Credits!

Turn Your Knowledge into Earnings.

tuteehub_quiz

Tuteehub forum answer Answers

Post Answer

No matter what stage you're at in your education or career, TuteeHub will help you reach the next level that you're aiming for. Simply,Choose a subject/topic and get started in self-paced practice sessions to improve your knowledge and scores.