Critical path lies along the activities having total float?

Question Bank Civil Engineering 1 year ago

5.73K 1 0 0 0

Option 1 : Positive

Option 2 : Negative

Option 3 : Zero

Option 4 : Same


 

Click Here For the Answer

Posted on 03 Jan 2024, this text provides information on Civil Engineering related to Question Bank. Please note that while accuracy is prioritized, the data presented might not be entirely correct or up-to-date. This information is offered for general knowledge and informational purposes only, and should not be considered as a substitute for professional advice.

Answers (1)

Post Answer
profilepic.png
MiclWapDA MiclWapDA Tuteehub forum best answer Best Answer 1 year ago
Same


Click Here For More

0 views
0 shares

No matter what stage you're at in your education or career, TuteeHUB will help you reach the next level that you're aiming for. Simply,Choose a subject/topic and get started in self-paced practice sessions to improve your knowledge and scores.

Similar Forum


Q

What is the capital of India

Option 1 : DelhiOption 2 : Panjab 
Q

What is the capital of Telangana

Option 1 : MumbaiOption 2 : HyderabadOption 3 : Pune 
Q

The gases used in different types of welding would include

Option 1 : oxygen and hydrogenOption 2 : oxygen and acetyleneOption 3 : oxygen, hydrogen, acetylene...