The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode$?

Question Bank Mechanical Engineering 1 year ago

2.89K 1 0 0 0

Option 1 : Early finish

Option 2 : Early start

Option 3 : Late start

Option 4 : Late finish


 

Click Here For the Answer

Posted on 03 Jan 2024, this text provides information on Mechanical Engineering related to Question Bank. Please note that while accuracy is prioritized, the data presented might not be entirely correct or up-to-date. This information is offered for general knowledge and informational purposes only, and should not be considered as a substitute for professional advice.

Answers (1)

Post Answer
profilepic.png
Naushad Malik Tuteehub forum best answer Best Answer 1 year ago
Early start


Click Here For More

0 views
0 shares

No matter what stage you're at in your education or career, TuteeHUB will help you reach the next level that you're aiming for. Simply,Choose a subject/topic and get started in self-paced practice sessions to improve your knowledge and scores.

Similar Forum


Q

What is the capital of India

Option 1 : DelhiOption 2 : Panjab 
Q

What is the capital of Telangana

Option 1 : MumbaiOption 2 : HyderabadOption 3 : Pune 
Q

The gases used in different types of welding would include

Option 1 : oxygen and hydrogenOption 2 : oxygen and acetyleneOption 3 : oxygen, hydrogen, acetylene...